April 8th Melville City Council Update

Paving & Walking Trail Rehabilitation and Sidewalk Installation projects are among the 6 capital projects to be undertaken in the City of Melville over the next number of months using money from Canada Community Build Funds.

When the 2024 City of Melville Budget was presented a plan was provided to utilize approximately $1.2 million of Canada Community Building Funds (formerly Gas Tax) to complete eight capital projects. 

But City Manager Jolene Tuchsherer says bids for these projects came in higher than budgeted so we they had to reassess the work that can be completed fiscally. 

“Administration is recommending that Council remove the Sewer Relining and Floodgate projects from the 2024 projects.The sewer relining program is one that we want to start back doing, but unfortunately this will have to wait and be budgeted in the 2025 capital budget. For the floodgate project Environmental Manager Ellert has begun developing a plan for this project and will provide a business case also for the 2025 budget.”



PROJECTS TO BE COMPLETED: 

1. Paving
• Queen Street (Halifax to 7th Ave)
• Columbia Street (8th Ave to Prince Rupert)
 • Dielschneider Road (7th Ave W to 9th Ave W)

2. Walking Trail Rehabilitation 
• Prince Edward to Park Boulevard Path
• Pool Path

3. Lift Station #3 pipe replacement

4. Manhole Relining

5. Welcome Sign Improvement Initiative

6. Sidewalk installation
• 7th Ave (Dielschneider to Highway #10 and Highway #10 to Heritage Road)
• Halifax Street and Main Street (Halifax to Main and Halifax/Prince William to the Mall Entrance)
• 3rd Ave E (Montreal Street to Manitoba Street) 

TENDERS AWARDED: 

1. Paving and Walking Trail Rehabilitation Project be awarded to Fedorowich Construction from Yorkton, SK in the amount of $689,613 plus taxes totalling $765,461

2. Sidewalk Installation Project be awarded to TR Concrete Ltd from Saskatoon, SK in the amount of $209,845 plus taxes for a total of $232,928

3. Lift Station #3 Pipe Replacement Project be awarded to TSL Mechanical (2009) from Lanigan, SK in the amount of $98,946 plus taxes for a total of $109,831

4. Manhole Relining Project be awarded to Topshot Concrete Systems from Saskatoon, SK in the amount of $80,800 plus taxes for a total of $89,688 